FOR BUILDERS & CONTRACTORS
Sourcing for
Builders & Contractors
Connect purchasing decisions to the site information that makes them usable. Cabinet sourcing for contractors is part of Foshan Bridge’s furniture and building-material sourcing and supply work. Start with the bill of quantities, current drawings and project stages so dimensions, product requirements and delivery priorities can be reviewed together.

BOQ to site.
Connect the details.
A CLEAR SOURCING PACKAGE
Turn the BOQ into a sourcing brief
A bill of quantities, or BOQ, is a starting point for scope and quantities. Add the specification and drawing references needed to understand each line. Identify the products included in this enquiry and the related work handled by other parties.
| BOQ field | Information to include |
|---|---|
| Item code and location | Building, floor, room or work area |
| Quantity and unit | Show how the quantity has been measured or counted |
| Specification | Product type, dimensions, materials and required configuration |
| Drawing reference | Current drawing number and revision |
| Site interface | Opening, service point, fixing or adjacent finish to confirm |
| Approval status | Ready to quote, awaiting information or ready for release |
| Proposed batch | Priority or site stage to discuss |
Keep missing information visible in the working schedule. A quantity alone does not confirm the configuration, and a reference photograph does not replace the drawing or performance requirement for a fitted product.
SITE INFORMATION
Resolve dimensions and interfaces before release
For cabinetry, review finished wall and floor dimensions, openings and appliance or service interfaces relevant to the design. For doors and windows, identify the opening information, handing, installation interface and project requirements that the selected supplier must review.
Name the person responsible for site measurement and the authority approving the final dimensions. If the site changes after a drawing is reviewed, identify the affected items and obtain a revised review before treating the earlier approval as current.
The kitchen cabinet collection can help establish the product direction for a kitchen package. The BOQ, approved drawings and quotation must then identify the actual configuration for that project.
- 01Finished openingWall dimensions and clearances
- 02Floor levelFinished floor and cabinet base
- 03Service pointsLocations relevant to the design
- 04Adjacent finishesEdges, junctions and fixing conditions
A CONTROLLED RELEASE
Link quotation and approval to the same revision

Compare products against one stated requirement. Check quantities, included fittings, assembly condition, packing and the agreed services alongside the goods price. Record proposed substitutions and their effect on the specification before approval.
A drawing approval should identify the revision being accepted. A price approval should identify the item and scope being bought. Keep open questions and excluded work separate, then connect the accepted documents to the order release.
Drawing work and paid samples follow the agreed project scope. Sample or prototype fees can be credited towards a subsequent order under the agreed conditions. Any project-specific test reports or compliance documents need to match the selected product and required use.
SITE-READY PRIORITIES
Discuss batches around site readiness
- 01
Identify the stage
Link each priority to a building, floor or work area.
- 02
Check readiness
Review supplier timing, site storage, access and handling.
- 03
Agree the batch
Confirm item lists, shipping arrangements and the effect on costs.
Mark which products are needed for each building, floor or work stage. Distinguish the preferred arrival period from the date the goods must leave the supplier, and identify site constraints such as storage space or access for larger items.
Phased supply requires an agreed item list, supplier acceptance and a workable shipping arrangement. Confirm the effects of storage, extra handling and separate freight before committing to batches. A requested site date is a planning input until the relevant production and transport arrangements are agreed.
Where the quotation uses our 30–40-day production period, it starts after drawings, materials and payment are confirmed. International transit is separate. The complete project programme also needs the relevant approvals, transport and site activities to be scheduled.
IDENTIFY EVERY PACKAGE
Specify packing marks and handover information
INFORMATION FLOW · ILLUSTRATIVE
Room / location
Use the same room or work-area reference in the item schedule.
Item / package
Agree the item reference, batch and package identification needed.
List / receipt
Connect the packing list to the receiving check and any discrepancy.
Discuss the identification needed by the receiving team: item reference, location or batch, package count and the relevant packing-list reference. Agree the available assembly and installation information with the selected products. The required format and detail should be part of the order scope.
Cabinetry and furniture can use cartons with pallets or wooden cases as appropriate to the product, without an additional packaging charge under the agreed packaging arrangement. Confirm the chosen format in the order; a specific packing construction or test result must not be assumed from that general arrangement.
Loading-related photographs can be provided. Any inspection report is agreed with the customer, and customer-specified third-party inspection is paid. Inspection scope and acceptance requirements should be resolved for the actual order.
NAME THE RESPONSIBILITIES
Allocate transport and installation responsibilities
Scroll across to compare all columns
| Activity | Record before relying on it |
|---|---|
| Transport / delivery point | Agreed trade terms and named destination |
| Clearance / unloading / local movement | Responsible party and the documents needed |
| Installation | Location, work scope, site conditions and agreed fee |
| Receipt discrepancy | Item / package references, photographs and order terms |
Record the trade terms and named delivery point in the quotation. Identify who handles destination clearance, unloading, local movement and installation, and which documents the receiving party needs. These activities have different responsibilities and should be agreed explicitly.
Paid installation personnel can be arranged for an agreed location and scope. Confirm the installation work, site conditions and fee before relying on that service in the site programme.
If an issue is found on receipt, keep the item and package references with photographs and the reported discrepancy. Use the agreed after-sales contact and order terms to determine the next action and responsibility for the remedy.
BEFORE QUOTATION
Questions before quotation
Can you work from an early BOQ?
Yes. Identify the missing specifications and the items that can already be reviewed. Final pricing and order release require the agreed product details and approvals.
Can an order be split across different site stages?
It can be discussed against supplier readiness, storage, packing and freight. Confirm the agreed batches and costs in the order; a BOQ batch column alone is not a delivery commitment.
Who checks whether a product meets project requirements?
Provide the required use and applicable specification with the enquiry. Relevant product evidence must be reviewed against those requirements by the responsible project parties before acceptance.